Ask for one dimensioned detail showing the actual tile, the proposed hook, the structural fixing position and the rail connection together. A roof hook is a purchasing candidate when the tile can return to its intended seated position, the arm clears it as the applicable instructions require, and the base can reach the specified fixing position. Release the order only for the roof zones covered by that evidence and the responsible project approvals.
A photograph can make two hooks look interchangeable. The difference may only become apparent when one base plate has to move sideways to reach the rafter, or when a deeper return on the underside of the tile occupies the space intended for the arm. Ordering by roof color, visible wave pattern or total hook height can leave a crew with a pallet of parts that fits the sample photograph but misses the attachment line on the building.
This guide is for buyers comparing quotations, product drawings and sample-fit records. It concerns the interface between a tiled roof and the solar mounting hardware. The project engineer and the roofing professional responsible for the building decide structural suitability and roof detailing. A dimensional comparison can identify a purchasing discrepancy without establishing a load rating, approving a roof penetration or providing an installation procedure.
Give each roof zone its own identity
Start with the smallest group of attachment locations that shares a known construction. A main roof and a later extension may look alike from the street. Their tile maker, batten arrangement or supporting members can differ. Identify each area on a roof plan, give it a short reference and use that reference in all requests for dimensions. A sample called “south roof, zone A, course near the approved survey point” can be traced. An image called “typical tile” is hard to challenge once a new person joins the order.
Collect the tile manufacturer's identification where available, the profile designation, photographs of the top and underside, the direction of the slope and the relationship to neighboring tiles. Show a scale in the same plane as the feature being recorded. A ruler lying across a high crest can give a misleading impression of the depth of a valley behind it. If the survey cannot identify the tile model, retain the survey evidence and mark the identification as open. A part number from an adjacent building should not fill that field.
Record which observations were actually made. A contractor might know the approximate rafter spacing from drawings but have opened only one survey location. In the RFQ, enter the drawing and the observed location as two separate evidence items. The supplier can then state which dimensions underpin its offer. The design team can decide whether another location needs examination before an order quantity is fixed. This distinction is especially helpful when roof areas were repaired at different times.
Ask for two views that share a reference
A section in the direction of the slope shows how the hook passes under a tile and emerges at its edge. A plan view shows the lateral distance between a permitted fixing line and the channel where the hook is intended to emerge. Ask the supplier to put a reference surface and a dimension direction on both views. A single perspective rendering is useful for recognizing the assembly, but it can hide which distances were measured vertically, across the slope or along the tile surface.
In the section, identify the support plane for the base, the base thickness if relevant, the underside and top of the projecting arm, the nearest tile surfaces, and the edge or rib that could collide with the arm. Show the overlying tile fully seated in the arrangement proposed for use. A single loose tile on a bench may sit at a different angle from an overlapping course. The sample record should say whether it represents the completed local stack or only one component.
In plan, mark the rafter or other designed support, the fixing positions permitted by the project, the intended axis of the hook arm, the tile side lap and the designed rail line. “Offset 20 mm” is incomplete when one team measures from the edge of a fixing hole and another measures from the rafter center. Ask the author to mark both endpoints, identify the left and right directions as seen looking up the roof, and describe how the opposite roof face will be represented. This avoids accepting a mirrored detail by accident.
Separate the adjustments before comparing offers
The word adjustable can refer to several different movements. A base may shift relative to a fixing line. An arm may be positioned at one of several discrete locations on a plate. A connection higher up may let a rail move vertically once the hook is in position. The buyer needs to know which movement solves which conflict, the usable extent of that movement and which other interfaces change when an adjustment is made.
The IronRidge technical brief for its All Tile Hook and flashings illustrates the distinction on one product. Its base has slots for lateral positioning relative to the rafter, the arm has three placement choices on the plate, and a vertical slot accommodates rail adjustment. Those three features answer different questions. Counting them as one continuous range could imply an arm position the product does not offer. The IronRidge All Tile Hook product page identifies QM-ATH-02-M1 and the XR and Aire rail systems. Carry the identified version and system into the comparison.
For each selectable position on a bid drawing, ask the supplier to indicate the resulting fixing location, arm position and rail connection. Where two settings are linked, request a table of permitted combinations. A maximum lateral reach from one setting and a maximum height from another may never occur together. Show the supplier exactly which combination your roof detail needs. This gives the technical reviewer a concrete configuration to evaluate before the buyer compares unit prices.
Read dimensions by their endpoints
The K2 SolidHook Vario 2 pantile entry for part 1000107 lists three separate height ranges. They are 49–58 mm under the bracket, 57–76 mm for bracket height and 128–156 mm overall. The entry places the hook in the SolidRail system and identifies rail mounting hardware as excluded. These facts belong together in a bid comparison. A buyer reading only the largest range could select the wrong dimension and also omit the hardware that completes the assembly.
If an inquiry asks whether a hook can clear an obstruction measured from the base support plane to the underside of the arm, an overall dimension to the rail connection does not close the inquiry. Return the measured section and ask for the matching dimension on the offered drawing. An offer remains open if the drawing uses a different datum and the supplier has not provided a justified conversion. Arithmetic based on the outline of a perspective catalog image is poor evidence for that conversion.
On small screens, swipe or scroll sideways to read every column. Keyboard users can focus the table and use the arrow keys.
| Buyer’s question | Evidence to put against the quotation | Decision when missing |
|---|---|---|
| Can the base reach the approved structural fixing? | Plan with allowable hole locations and lateral settings | Refer the fixing detail to the designer |
| Does the arm pass the seated tile? | Actual profile section with endpoints of the specified clearance | Request a representative fit record |
| Can the rail meet its intended level? | Rail connection detail for the selected arm position | Keep the rail interface open |
| Which parts form the weathering detail? | Roof-zone drawing and separately identified flashing components | Return the scope to the roofing reviewer |
| What arrives in a carton? | Orderable codes, units and inclusions for the complete configuration | Compare the completed set before award |
Keep clearance tied to one product and one tile surface
In the K2 Tile Hook 3S quick guide, step three for kit 4001294 shows a minimum spacing of 5 mm between the bracket and tile. The diagram identifies the surfaces that give that number meaning. This is an example for the Tile Hook 3S covered by that guide. The separate Vario 2 catalog ranges describe another component. Neither the Vario 2 entry nor the presence of a similar arm on a competing product transfers the 3S spacing requirement to the other hook.
Ask for the current instruction applicable to the part and market actually offered. Keep the document reference beside the proposed gap on the section. Also ask what physical state the gap describes. A nominal drawing, a seated sample measured at rest and a designer's assessment of clearance under the governing load are different kinds of evidence. Record the measured state as observed. Carry any remaining loaded-condition question to the responsible designer with its own decision field.
Some apparent clearance problems come from observing only the upper tile. An arm that lets the covering tile settle could still bear on the lower tile. Conversely, visible space over the lower tile does not show that a hidden rib or nib on the covering tile misses the arm. Request viewpoints that reveal each surface named by the applicable instructions. If the nearest point is hidden in the installed photo, a section or a second controlled observation may explain it better. Select the evidence before asking the supplier to photograph more locations.
Screen a dimension stack before ordering a sample
Consider an invented drawing for a proposed hook and a surveyed lower tile. Both dimensions are perpendicular to the same base support plane at the same cross-section. The drawing places the underside of the selected hook arm at 55.0 mm with a possible variation of 0.6 mm in either direction. The survey envelope places the top of the lower tile at 49.2 mm with a possible variation of 1.0 mm in either direction. Assume for this exercise that the project reviewer has specified a 5.0 mm minimum at rest measured along that perpendicular at this section of the hypothetical assembly.
At the nominal values, the gap is 55.0 minus 49.2, or 5.8 mm. For a conservative screening calculation in which the extremes can coincide, the lowest arm surface is 54.4 mm and the highest tile surface is 50.2 mm. The resulting 4.2 mm gap is 0.8 mm below the assumed requirement. If the actual instruction specifies the nearest gap anywhere across the arm, request the whole interference envelope. A neighboring ridge or an edge of the arm can set that minimum outside this section. The calculation does not predict physical contact. It shows why the nominal result alone cannot support the proposed release decision.
The purchasing action is to hold that configuration and ask the responsible reviewer to check the input bounds, possible settings and applicability to the surveyed zone. If the extremes cannot occur together, the bidder can return the controlled drawing that establishes the relationship. If a different setting is offered, request the same two dimensions for that setting. The screen covers one static section. It does not resolve upper-tile fit, structural deflection, fastener position or weathering, and none of the invented dimensions is a specification for either manufacturer's hardware.
Use a fit sample to close the right question
For a representative fit review, list the exact hook revision, hardware set, sample tile identity, neighboring tile arrangement and the support arrangement being represented. Identify the roof zone the sample is meant to cover. Ask the responsible field team to document how representative the sample is and record any differences from the building. A spare tile borrowed from a different lot may be adequate for recognizing a profile and inadequate for signing off a specific clearance.
Define acceptance questions in advance. Does the lower tile clear the arm at the designated point in the required assembly state? Does the overlying tile settle against its intended bearing surfaces? Is the fastener location within the designer's permitted region? Is the rail connection accessible in the position used for the sample? A photograph with all four items visible is useful, but each still needs its own observation. An attractive overall assembly should not automatically close an unobserved measurement.
Tie any approval to the version shown. If the bidder moves the arm to a different position after the trial, the old observation still describes the first setting. Annotate the first trial with the reason for the change and ask for the evidence affected by the second setting. An unaffected tile identification can be reused. A clearance measured at the previous arm position ordinarily needs a new justification. This saves repeated surveys while preserving the logic behind the release.
Send the tile and hook drawings. Include the roof-zone reference, the outstanding fit question and the proposed rail system so that the response can address the correct interface.
Separate tile replacement from the flashing beneath it
A quotation for a hook, a deck flashing and a replacement tile describes three different purchasing lines even when the parts appear together in the same photograph. On the IronRidge tile replacement flashing page, the manufacturer identifies flat, S and W profile options and says it sells hooks and flashings separately. Its technical brief also illustrates a deck flashing over the mounting plate as another element of its specific system. A bidder who includes one of these parts may still have excluded another.
Ask the roofing reviewer to identify the approved detail at the covering and the water-shedding layer below it. Have the bidder identify which bill-of-materials line supplies each component, which party supplies anything excluded and which drawing establishes compatibility. Include neighboring tile geometry where it determines whether a replacement profile can sit correctly. The physical hook can clear the tile while the proposed replacement profile is still wrong for the adjacent course.
Record the selected solution for each roof zone. A change from retaining the original tile to replacing it may affect spare quantities, color selection, roof appearance and the roofing team's scope. A material substitution on a small accessory can therefore affect both purchasing and project acceptance. The roof flashing buyer guide covers the wider water-shedding questions. Here the release concerns the fit between the proposed hook, the selected tile treatment and the specific course identified on the roof plan.
Compare two bids with a common roof-zone schedule
Consider a hypothetical order with 30 planned attachment locations in zone A and 18 in zone B. For this exercise only, the project designer has already scheduled the locations. Zone A uses a known flat profile. Zone B uses an S profile from a roof extension. The 48 locations are a bill-of-materials example, not a recommendation about how many attachments a building needs.
Bid One offers 48 adjustable hooks and 48 rail connection sets. Its submitted section is for zone A alone. The written offer says tile treatment is by others. Bid Two lists 30 hook assemblies for zone A and 18 for zone B, together with 18 S-profile replacement flashings. The bid shows both tile profiles but leaves the rail interface as a separately purchased line. Neither quotation by itself describes 48 complete, approved attachment sets. Counting the larger package or comparing the two hook prices would miss the actual scope gap.
Start by marking which comparisons are ready. The design team can examine Bid One's zone A section if it uses the required datum and fixing location. For its zone B row, request the missing section and confirmation of the tile treatment from the named party. That missing information does not establish that the hardware will fail. For Bid Two, match the 18 replacement units to the zone B roof detail, then obtain the rail connection codes and quantities for both zones. Keep structural and roofing approval as separate fields even when both reviewers respond on the same date.
A purchasing team can now ask both bidders to price the same completed bill. Any costs assigned to the roofing contractor should stay visible in the comparison. If a bidder offers a substitute only for zone B, retain a separate subtotal and approval condition for that zone. An accepted zone A sample should not quietly become the reference for all 48 locations simply because the packages travel on one purchase order.
Prepare a release decision the warehouse can follow
An engineering approval describing a roof area is useful to receiving staff only if incoming parts can be matched to it. Translate the approved assembly into orderable identifiers for the hook, rail hardware, flashing choice and any agreed ancillary parts. Include quantities per approved location and the supplier's ordering unit. A line expressed in boxes can look like a line expressed in individual hooks when both quantities are small integers. Ask for a packing schedule with the units written out.
Specify which parts must remain grouped by zone and which identical parts may be pooled. If zone A and zone B share a hook but require different profile flashings, a common hook carton may be acceptable while two profile codes still need separate labels. Where the attachment itself changes, preserve its full code on the receiving list and on the handover to the installer. A photograph of two near-identical brackets cannot reliably replace those identifiers once the bags have been opened.
For receiving inspection, identify visible things that distinguish the approved items. A matching product label, hole pattern, arm shape and rail-interface detail can support identification against the controlled drawing. Record who handles discrepancies when identification is inconclusive. Receiving staff should not have to determine structural suitability from a dimensional match or accept replacement tile shapes by color alone. The correct disposition may be as simple as holding one mixed carton until the supplier identifies its contents.
Ask about loose components and break-pack orders before choosing how many spare sets to purchase. A spare arm without its compatible connection can leave the team unable to replace the approved assembly. A spare flashing of the wrong tile profile does not solve a shortage in a different zone. Build the spare list using the approved configuration and the project's service plan, with no assumed breakage percentage. The supplier's actual pack size can be accounted for separately from the number of spares the owner wants.
Decide what a revised drawing must reopen
Suppose the supplier can provide the original hook body but changes the base plate. Identify which earlier evidence depended on the old base. Hole positions and the permitted structural fixing may need review again. Where the replacement changes the position of the arm relative to the rafter, revisit the tile interference check too. The tile identification itself can remain a valid survey fact. A change record that names the affected evidence is more useful than asking the field team to repeat every observation.
A rail change has a different path. Confirm the connection geometry, included hardware and any effect on the rail level relative to the selected hook setting. Follow the consequences to other parts only where the revised detail changes their interface. For example, the module clamp-zone guide becomes relevant if the design team changes rail positioning relative to the module. It need not become part of every tile profile review.
Changes can originate at the site as well. A replacement tile sourced during roof repair might have a similar visible pattern but a different return on its underside. Keep the previous approval attached to the original zone and add a new row for the repair area. Ask which previously approved dimensions still apply and whether an affected representative sample is available. This way a small repair area can be managed without delaying the order for unrelated locations.
Write the acceptance language before comparing price
Ask each bidder to return a marked drawing or an evidence reference against the same four items: roof-zone identity, permitted fixing location, clearance at the seated tile and rail connection for the chosen setting. Add the selected flashing detail and identify inclusions, exclusions and the party responsible for each excluded part. If the supplier needs more site information, request the precise missing measurement and its endpoints. A reusable response line is “Zone ___, drawing and revision ___, chosen hook and position ___, fixing line ___, observed gap and endpoints ___, rail kit ___, flashing supplied by ___, accepted or open ___.” Leave the unresolved measurement blank and name its owner.
Use plain decision terms agreed with the project team. An item may be ready for quotation, ready for a sample fit, accepted for a named zone or held for further evidence. Record the decision owner and the drawing or trial it covers. These terms help prevent a commercial response from being mistaken for a technical release. They also help procurement compare offers fairly when one bidder has completed a site-specific drawing and another has provided only a catalog entry.
When approaching a supplier, attach the drawing and the roof-zone schedule first, then specify quantities, desired delivery grouping and the response format. A request for solar mounting brackets can then describe a specific interface rather than an open-ended request for roof hardware. Send the roof-zone schedule for quotation with the part codes under consideration and any outstanding approvals clearly identified.
Buyer FAQ
Can I approve a hook if its catalog supports my tile profile?
Use that information to shortlist the product. For release, connect the actual profile and support arrangement in the relevant roof zone to the selected product drawing. Ask which arm and base settings were evaluated, how the covering tile sits and where the hook emerges. A catalog family description alone leaves those local relationships unresolved.
How should we compare two suppliers that quote different height ranges?
Mark the start and end surfaces for the requested dimension on the same section drawing. Ask both suppliers to identify the dimension their ranges describe. Compare matching quantities at the selected settings, including the rail connection where relevant. Separate under-arm space, arm height and overall assembly height into distinct lines so a larger overall number cannot stand in for tile clearance.
Can one sample cover two roof zones?
It can support both decisions if the responsible reviewer documents why the tile geometry, fixing detail, assembly settings and other material conditions are representative of both. If one roof was extended or retiled, identify whether that changes the critical interface. A common tile color or a common hook code provides too little information to settle the question.
Is a minimum gap found in one hook manual valid for another hook?
Get the instruction for the offered code and ask the technical reviewer to identify the relevant surfaces and condition. Record any uncertainty for the supplier to resolve. A value published for one named product is useful evidence for that product. Applying it elsewhere requires a documented technical basis, even if the two brackets look alike.
Does a tile replacement flashing automatically include deck flashing or rail hardware?
Check the actual order lines and their inclusions. Ask the roofing reviewer to specify the weathering detail for the location and the rail supplier to identify the required connection. The buyer can then reconcile the individual parts to the complete approved set. If another contractor will provide an item, name that party on the comparison sheet.
What information should be requested if a survey point is inaccessible?
Name the unverified roof zone, the reason it was inaccessible and the particular interface still in question. Ask the responsible site team what alternative evidence can be obtained safely. Existing drawings may justify a provisional quotation but the project reviewer should state the condition for releasing the affected quantity. Keep an estimated dimension visibly separate from an observation.
What should the buyer retain after the order is placed?
Keep the approved zone schedule, drawings with revisions, exact product codes, sample-fit record, scope of supply and any written exceptions with the order. Give the receiving and installation teams the identifiers needed to match deliveries to that record. If a substituted part or new roof condition appears later, the team can trace which previous decision is affected and who must reopen it.