Specify a DC solid-state relay by the load it must control, the current allowed when commanded off, and the cooling arrangement that makes its operating rating valid. A large current number and a control-voltage label do not establish that a device will switch the intended circuit, reset a sensitive load, or provide the isolation required for service.
The purchasing deliverable should identify an exact relay, its output technology, its external protection and mounting parts, and the evidence needed for the assembled application. Keep control-input isolation separate from separation of the power circuit. A control signal that says OFF is an operating instruction; it is not independent proof that the load has been disconnected.
This guide concerns procurement of an electronic DC switching assembly. Mechanical switching has different evidence requirements, covered in the DC contactor interruption and polarity guide. No manufacturer example below establishes SINAWATTS stock, component authorization, test capability or application approval.
Identify the output circuit before comparing current ratings
Begin the RFQ with a block drawing showing the source, relay output terminals, load and return path. Label which terminals carry control power and which carry load power. A relay with a DC control input may still have an AC output. Purchasing solely by the input label can therefore select the wrong switching device before any thermal or reliability comparison begins.
Ask the supplier to identify the exact output structure and its permitted current directions. Do not infer bidirectional blocking from a generic MOSFET description or a two-terminal package. The manufacturer's circuit and operating instructions must support any reverse-voltage, reverse-current or regeneration condition required by the equipment.
Separate these operating events: normal forward load current, current flowing back from the load, a reversed supply connection, and a transient across the open output. They may look like a reversed arrow on a drawing, but they have different durations and consequences. List the events actually possible and leave unsupported ones as unresolved engineering requirements.
The supplier response should also state the allowed switching mode. Occasional on/off operation, rapid pulse control and proportional power control are different duties. A switching-frequency figure from one condition does not establish performance with another load, temperature or drive waveform. Request the relevant restrictions without treating a timing parameter as a complete control recommendation.
For equipment that already uses a mechanical contactor, avoid asking for a universal electronic replacement. Preserve the circuit's original function, including any service disconnection, feedback or fault response, and review which parts an SSR can actually perform. The device substitution should follow that functional review.
Read a real DC relay example as a set of conditions
The Sensata 1-DC series sheet for D1D60, D1D80 and D1D100 illustrates why a headline label is insufficient. Its output table separates a recommended operating range of 1–72 VDC from an absolute maximum of 100 VDC. That distinction prevents a buyer from interpreting the family headline as permission for continuous operation at the absolute limit.
The same table lists maximum off-state leakage at rated voltage, minimum load current and required cooling alongside load-current ratings. Selected entries are summarized below solely to demonstrate how to read this particular document. They are not interchangeable limits for other relays or approval of a proposed installation.
On small screens, swipe or scroll sideways to read every column. Keyboard users can focus the table and use the arrow keys.
| Manufacturer item | D1D60 | D1D100 |
|---|---|---|
| Maximum off-state leakage at rated voltage | 0.1 mA | 0.3 mA |
| Minimum load current | 5 mA | 5 mA |
| Listed heat-sink thermal resistance for rated current at 40°C | 1°C/W | 0.5°C/W |
The document also provides thermal derating information and application notes. Its input/output/base dielectric-strength specification concerns those named boundaries; it does not state that the two output terminals become an open mechanical isolating gap. Use the exact order code, options and conditions when requesting supporting data. Sensata 1-DC series original data sheet
For bid comparison, add a fourth column for your requirement and a fifth for the supplier's evidence. An empty evidence cell should remain an open item, even if the offered nominal current is higher. Higher current can coincide with different leakage, mounting or control behavior; it is not automatically a better substitute.
Keep manufacturer limits separate from the project's acceptance limits. A purchaser may require a smaller off-state current or a different cooling envelope. That does not change the catalog specification; it changes which candidates can satisfy the intended assembly.
Define the off-state behavior the load actually needs
Leakage is important when a downstream load remains sensitive to a small current. State the load's required off condition in observable terms: released relay coil, dark indicator, reset controller input, discharged node, or another documented behavior. These are not equivalent electrical limits, so a single maximum leakage number cannot replace the load requirement.
OMRON's microload guidance distinguishes AC-output and DC-output considerations and specifically discusses load reset failure caused by DC SSR leakage. It also distinguishes power-MOSFET arrangements from other output types. This supports checking the exact relay and load combination rather than applying one universal minimum-load rule. OMRON microload and leakage FAQ
Consider a deliberately simplified, hypothetical off-state model. Assume a relay leaks a constant 0.2 mA into a purely resistive 10 kΩ load at the available supply voltage. Ohm's law gives 2 V across the resistor. If a project requires less than 1 V in that state, this model exposes a possible incompatibility. It does not predict the voltage of an actual electronic input with nonlinear protection, internal pull resistors or capacitors.
The same simplified model with a 2 kΩ resistor gives 0.4 V. A parallel discharge or bleeder path may therefore change behavior, but adding one creates on-state dissipation and other design questions. Do not prescribe a resistor from this example. Request an approved circuit and verify both states with the actual load.
Specify the measurement conditions: supply voltage, temperature, instrument impedance, connection points and stabilization time. A high-impedance meter may reveal a floating-node voltage that has little relation to available load current. Conversely, loading the circuit with an unrecorded meter or resistor may hide a reset problem. The evidence needs both the electrical method and the intended operating result.
Separate control-input OFF from output OFF
Review the controller output as a circuit, not merely as a voltage label. Record its asserted voltage, available drive current, residual current when off, wiring length and shared return arrangement. Compare these against the exact relay's turn-on and must-turn-off requirements under the stated conditions.
An LED on the SSR is useful for observation but cannot replace a measurement of the power path. OMRON explains that an operation indicator responds to the input circuit and does not establish that the output element is conducting correctly. The purchasing test should therefore distinguish input command, output electrical state and load response. OMRON technical guide, operation indicator section
Ask what happens during controller startup, loss of control power and supply restoration. A diagram showing only the steady commanded states leaves these transitions unspecified. The engineer should define whether the load must remain off, resume automatically or wait for a separate authorization. Procurement then requests evidence for that defined sequence.
Where the control wiring connects to a transistor output, identify leakage and any diagnostic pulses on that output. A relay input may see conditions that a simple voltage measurement misses. Do not approve a wiring change just because the relay indicator appears dark during one bench observation.
For multiple channels, document common terminals and grouping. A shared control return can create dependencies that are absent from a single-channel demonstration. Include the channel arrangement in the approved drawing and record which configuration the supplier evaluated.
Send the load-state requirements and control wiring for a DC relay RFQ. Include the exact controller output information and describe the required behavior during power loss and restoration.
Compare conduction loss without inventing a thermal rating
For a MOSFET output, a useful simplified conduction-loss model is current squared multiplied by on-state resistance. For an output characterized by an on-state voltage drop, power is current multiplied by that drop. OMRON presents both approaches and notes that MOSFET on-state resistance increases with junction temperature. These are starting models, not substitutes for the manufacturer's thermal data. OMRON heat-radiation design guidance
Take a hypothetical switch with a stated resistance of 0.020 Ω at a defined condition. At a steady 10 A, the model gives 10 × 10 × 0.020 = 2 W. At 20 A it gives 8 W. Doubling the current produces four times the conduction loss in this constant-resistance model.
If an independently justified hot-condition resistance were 0.030 Ω, the corresponding 20 A loss would be 12 W. That resistance is an invented example value, not a universal temperature multiplier. The calculation shows why an unqualified room-temperature resistance can understate heat; it does not establish a permissible current or junction temperature.
For variable current, a steady average-current substitution can also be misleading. Request the actual duty waveform and the manufacturer's supported loss calculation. Switching losses, transient heating, load peaks and thermal time constants may matter. The final review should use an application-specific method rather than stretching this elementary screen into a qualification.
Require each bid to identify the data used for its thermal claim. Useful answers include a named curve, mounting condition, case-temperature limit and test configuration. An unsupported statement that a relay is “oversized” leaves the heat path unresolved.
Purchase the cooling arrangement as part of the assembly
A heat sink is not just a block of metal with matching holes. Its performance depends on mounting orientation, airflow, surrounding equipment and the thermal interface. Identify the intended heat sink or approved specification, interface material, fasteners and assembly instructions as controlled parts of the quotation.
Ask where the quoted ambient temperature is measured. Room air, enclosure inlet air and the local air beside the relay can differ. An installation that places several heat-producing parts together should be evaluated in the intended arrangement. The enclosure thermal-budget guide covers that broader heat balance.
Separate the relay-to-sink interface from sink-to-air performance. A low catalog thermal resistance does not prove that a damaged surface, missing pad or incorrect mounting process transfers heat correctly. Receiving and assembly records should establish that the specified interface was actually installed.
The RFQ should identify which thermal evidence is already available and which remains required. A supplier may be quoting a bare component, a component with loose cooling parts, or an assembled unit. These are different deliverables. Avoid accepting a thermal claim for a fully assembled reference configuration when buying only the relay.
Where a fan is part of the approved cooling arrangement, record its operating state and the required response to loss of airflow. This is a system design question, not an opportunity to assume continued full-current operation. A thermal protection feature, if documented, still needs a defined recovery behavior and limits.
Keep switching protection and service isolation distinct
An SSR may fail in a conductive state. OMRON's safety precautions identify short-circuit failure as a principal failure mode and advise against relying solely on an SSR to shut off load power when it fails. The application must include the independently designed means needed for its fault response. OMRON SSR safety precautions
This does not mean that any contactor or breaker automatically creates a compliant safety system. The equipment engineer must define the required function, isolation boundaries and verification. Procurement should request the approved architecture and avoid silently assigning a safety function to a component that was selected for ordinary switching.
Service disconnection also requires its own evidence. Input/output galvanic separation, output leakage, semiconductor failure behavior and a lockable isolating device address different questions. The lockable battery-disconnect guide explains the separate sourcing decision for that equipment function.
For overcurrent protection, ask for coordination evidence tied to the exact SSR and protective device. A fuse current rating alone does not show that the semiconductor survives the relevant fault. Keep normal inrush, permissible surge behavior and prospective fault conditions separate in the evaluation record.
Inductive-load protection likewise belongs to the circuit drawing. The selected relay manufacturer may require a particular suppression arrangement; its influence on load release must be reviewed. Do not substitute a convenient protective component without updating the controlled design and acceptance evidence.
Specify response timing at the load
State where the required switching time is measured. The delay from a controller command to an SSR output change is not necessarily the delay until a motor stops, a valve releases or a downstream capacitor discharges. A report that measures only the relay terminals cannot establish the final equipment response without the relevant load evidence.
For a hypothetical procurement requirement, suppose a controller must remove a load-enable condition within 30 ms of a command. The relay's documented switching delay might occupy only part of that interval; controller processing, output-drive behavior and the load's release mechanism can occupy the rest. Do not subtract a typical relay delay from 30 ms and call the remainder a guaranteed margin. Request limits and measurements for the specified chain.
Define the trigger event, threshold used to detect the output change, instrument timing accuracy and load-state criterion. If a protective suppression circuit is included, identify it in the same timing record. A protection change that helps the switching element may also alter how quickly the load releases, so its evaluation belongs to both reviews.
Record whether the result covers only a single transition or the complete repeated duty. A clean first event after a long idle period does not establish performance after the equipment reaches its operating temperature. The RFQ can request representative operating sequences without inventing a universal cycle count or demanding tests that the project does not need.
Build a test matrix around failures a buyer can recognize
Organize acceptance evidence by operating condition rather than by a long list of instrument names. Each row should connect a defined input, an expected result and a clear decision. A supplier can then distinguish an existing qualification result from a proposed test that has not yet been performed.
On small screens, swipe or scroll sideways to read every column. Keyboard users can focus the table and use the arrow keys.
| Evaluation condition | Evidence to request | Unresolved if missing |
|---|---|---|
| Maximum normal load and local temperature | Configuration, stabilization and temperature records | Continuous operating suitability |
| Minimum intended load, command off | Leakage method and actual load reset behavior | Reliable off state |
| Controller power loss and restoration | Command and load-state sequence | Restart behavior |
| Approved installation and cooling | Part identities, orientation and interface records | Transferability of component data |
Document sample identity, relay options, heat-sink identity and controller configuration in each report. A photograph can support traceability, but it does not replace measured values or an unambiguous wiring diagram. Require the report to distinguish typical characterization from an acceptance result against specified limits.
Record deviations even when the load appears to operate. For example, a supplier may test with a different heat sink or omit the final cover. Such results may still be informative, but their scope should remain visible. Do not silently treat them as evidence for the final assembly.
Determine who owns each open item before releasing the purchase order. Some questions require the equipment designer, some the relay manufacturer, and some the assembly supplier. Naming an owner prevents a quotation from becoming an accidental design approval.
Preserve the approved configuration through production and service
A practical release package includes the exact order code, approved drawing, protection references, cooling parts, acceptance limits and controlled deviations. Give that package a revision identifier that can be matched to the delivered lot. The purchasing record should make it possible to distinguish an approved alternative from an unreviewed substitution.
Changes to the semiconductor relay can affect more than current capacity. A replacement may have different off-state leakage, control-input requirements, switching time or mounting constraints. A service technician should not be forced to infer equivalence from a similar case or a larger printed current.
Define the permitted substitution process. The supplier should identify proposed differences before shipment, with the specific requirement each difference affects. Reuse existing evidence only where its conditions remain applicable. Any new evaluation should identify the affected boundary rather than repeat unrelated checks.
Keep accessory substitutions equally visible. An alternative thermal pad, terminal cover or mounting plate can change the finished configuration even if the relay part number stays the same. The approved bill of materials should identify which substitutions require engineering review.
For receiving inspection, distinguish identity verification from destructive or energized qualification. A routine lot check can confirm labels, options, documentation and physical completeness; it should not be described as proof of every thermal or fault-performance claim. The acceptance plan must state what that check establishes and what evidence remains inherited from the approved configuration.
If the project includes cable assemblies, labeling or a defined assembly package, use the OEM/ODM project scope page to frame the requested deliverables. Availability and any inspection or test service must be confirmed for the actual quotation rather than assumed from this guide.
Buyer FAQ
Does a DC control input mean the relay can switch a DC load?
No. Input power and output switching are separate specifications. Identify the exact load-side rating and output technology, then check the permitted voltage, current direction and operating mode. A control terminal labeled for DC does not establish a DC-output design. Include both sides of the wiring diagram in the RFQ so suppliers cannot answer only the control-voltage portion.
Is a higher current rating always the safer purchase?
No. It can bring different leakage, drive requirements, cooling needs or package constraints. Compare candidates at the actual load, ambient and mounting conditions. The manufacturer's current rating remains conditional. An oversized headline number does not correct an unsuitable output type or establish that a sensitive load will reset when commanded off.
Can a voltmeter reading prove that the output is isolated?
A voltage reading alone cannot establish an isolation function. The reading depends on the circuit and instrument impedance, and semiconductor outputs can pass leakage current when off. Define the service or fault-isolation requirement separately and obtain the appropriate design evidence. Do not use a dark indicator or a single no-load measurement as a substitute.
Can the input indicator confirm that the load is off?
It indicates activity in the input circuit, not independent integrity of the power path. A failed output can differ from the commanded state. If the equipment requires confirmation, the engineer must define an appropriate monitoring method and acceptance criteria. Purchasing should request that documented function rather than assume an indicator supplies it.
Is a heat sink with the right mounting holes sufficient?
No. Mechanical fit is only one condition. Thermal resistance, installation orientation, airflow, interface material and surrounding heat sources also matter. Request the complete approved cooling arrangement and the evidence supporting it. If a supplier proposes another sink, the revised configuration needs review against the same load and environmental requirements.
Can an external resistor solve every off-state reset problem?
No. A resistor may alter the circuit's off-state voltage but also dissipates power when energized and can affect other functions. The simple calculations in this guide are screening examples, not design instructions. Use a reviewed circuit with the actual load, relevant temperature limits and both operating states documented before accepting such a change.
What should accompany a quotation request?
Send the source and load ranges, load type and waveform, required off-state behavior, controller interface, temperature and cooling envelope, installation drawing and fault-response scope. Identify required reports and who approves alternatives. Ask suppliers to separate the bare relay, accessories, assembly work and any proposed verification. This makes exclusions visible before a price comparison.
Send the DC switching diagram and acceptance matrix for a complete RFQ. Request a response against each operating condition and keep every unsupported substitution or performance claim open until evidence resolves it.