Release a solar ground-screw order against an accepted foundation design for the actual site, supported by the required investigation, tests and installation controls. A catalog length, an impressive driving torque or a supplier's generic pull-out result does not establish that the proposed foundation will support a particular array in its actual soil.
For the buyer, the useful output is a foundation release schedule. It connects each location or accepted site zone to the specified screw, head connection, design reference, test basis and installation acceptance record. This makes it possible to purchase the right components, distinguish approved alternatives and hold unresolved positions without losing track of the rest of the project.
This guide concerns ground-mounted PV foundations. It is separate from the roof structural-screw guide, where the supporting substrate and connection are different. It does not size foundations, prescribe installation torque or authorize site testing. Those decisions belong to the project's qualified designers and approved installation procedures.
Identify what the bidder is actually supplying
Clarify whether the offer covers loose screws, a complete foundation system, design support, site investigation, test installation, production installation or the full installed foundation. Two quotes with the same unit count can place very different responsibilities on the buyer. A low component price may exclude the evidence necessary to release those components for use.
Ask for a scope schedule alongside the price. Name the party responsible for the soil information, array reactions, foundation design, test plan, installation method and final acceptance. State which approvals are required before manufacturing or delivery. If one party relies on information supplied by another, identify that information and its revision.
The boundary at the top connection is particularly important. A supplier may provide a screw and flange while another supplier provides the solar rack. The flange's hole pattern, connection hardware and permitted geometry must agree with the rack design. Do not allow the foundation order to assume that a site-made adapter will resolve an interface that nobody has reviewed.
A solar mounting component enquiry can start this discussion, but a category page does not establish availability of an engineered ground-screw system or project design services. Request explicit confirmation of the proposed supply scope and avoid attributing capabilities to SINAWATTS that have not been documented for the enquiry.
Start with the site zones rather than one generic soil description
Provide the available geotechnical information and an accurate site plan to the responsible foundation designer. Mark areas of fill, previous excavation, slopes, drainage changes and other features already identified by the site investigation. Purchasing should not reclassify soil from photographs or replace a missing investigation with a statement that the ground feels firm.
Keep the investigation points visible on the drawing. A report from another part of a large property may provide context without covering the proposed array footprint. Ask the geotechnical professional to state the relevant area and any limitations. Where uncertainty affects the proposed foundation, list it as an open issue rather than presenting the entire site as one confirmed soil type.
KRINNER's project-process description links subsoil assessment, foundation planning, site load testing and installation. It describes using the soil information and structural loads to select the foundation and using tests to confirm planning assumptions and installation parameters. This is a useful example of an evidence sequence, not permission to copy a KRINNER design or apply its parameters to an unrelated screw.
Ask how changed ground conditions will be handled during construction. The contract should define who assesses an unexpected condition and who can authorize an alternative. A purchasing schedule can include provisional quantities for an accepted option, but it should not give the installer unrestricted authority to change foundation types, depths or positions to maintain production speed.
Make the load information usable at the foundation interface
Ask the rack designer for the foundation reactions and the reference geometry used to calculate them. The document should identify load cases or combinations, coordinate directions, application points and the design basis. A total array weight alone does not describe every action that the foundation design needs to consider.
Separate the information used for engineering from simplified purchasing labels. A quotation may say uplift-resistant, but the technical file needs the actual accepted design references. If a load table uses compression as positive and the foundation supplier assumes the opposite, the drawing and calculation interfaces need correction before material release.
Do not divide a total array load equally by the number of screws unless the responsible design actually supports that distribution. Different positions can have different reactions. The procurement schedule should follow the designer's location groups and foundation types, not a convenient average invented to make all order lines identical.
Record the load application height and connection geometry. A replacement flange or an increased exposed length can change the interface reviewed by the designer. When the rack supplier changes its support detail, require a documented foundation review. The buyer's useful question is which drawing and reaction schedule support the proposed component, rather than whether a visually similar part seems strong enough.
Read a capacity document without transferring its approval
A product evaluation report can provide valuable evidence, but only within its stated product and application scope. Check the report holder, covered models, revision and relevant conditions. A report number on a quotation does not prove that the delivered screw, flange or installation matches the evaluated system.
The official ICC-ES ESR-4226 report, reissued March 2026 and revised June 2026 in the version checked, covers named AGS ground-screw systems. It separately addresses top connection, shaft, thread and soil capacity and describes the overall system limit using the governing component capacity, with the required analysis. This illustrates why a soil value alone cannot establish the complete foundation rating. It is not certification of SINAWATTS products or every screw-shaped foundation.
For a different offered system, request its own applicable evidence. Do not borrow a table for the same nominal shaft diameter when the thread geometry, top connection, material or installation conditions differ. Where the manufacturer proposes equivalence, ask the responsible designer to identify the basis and accept the specific configuration in writing.
Keep marketing data and design values visibly separate in the review pack. A photograph of a successful installation, a demonstration video and an environmental declaration may each have a purpose, but none should be silently relabeled as the project's foundation capacity calculation. The supplier should identify which document answers each open technical question.
Keep four different numbers in four different columns
A supplier return can contain several values expressed in force units while describing different things. Ask the reviewer to label them before comparing bids. Matching units do not make the values interchangeable.
On small screens, swipe or scroll sideways to read every column. Keyboard users can focus the table and use the arrow keys.
| Value in the return | Its stated purpose | What it cannot establish alone |
|---|---|---|
| Foundation reaction | Input from the supported structure's design | Resistance of an unknown screw-soil combination |
| Test load | Load applied under the approved test program | The final allowable project capacity without interpretation |
| Component capacity | Limit for the identified component and conditions | Capacity of the entire installed foundation |
| Released design value | Result accepted for the specified project configuration | Approval of an unreviewed substitute or different site zone |
Attach the source document and units to every value, including the applicable design basis. If one bidder labels a value ultimate and another labels its value allowable, return the comparison for engineering reconciliation. Purchasing should not insert a convenient safety factor to manufacture comparability.
Purchase a test plan that can answer the design questions
Ask the foundation designer to define the required test program before the test contractor mobilizes. The plan should identify representative locations, foundation configurations, loading directions, measurement requirements, acceptance criteria and reporting obligations. It should also state how the results will be used and what conditions require additional investigation.
Distinguish a design verification program from production acceptance checks. A test intended to investigate behavior and a check intended to confirm a production installation can have different purposes and consequences for the tested foundation. The plan must say whether a test foundation may remain in service and who decides that disposition.
KRINNER's test-equipment page distinguishes equipment for tensile, compressive and horizontal loading. The purchasing lesson is narrow but important: a device's advertised maximum force does not prove that it can deliver the project's complete test arrangement. Ask the test provider to match the required direction, setup and measurement scope to the accepted plan.
Before mobilization, identify who releases the site work and documents relevant underground-service clearances and access restrictions. The KRINNER process description specifically flags required underground-cable plans and local clearance needs before tests. A supplier's agreement to attend is not proof that the site is ready for intrusive work; the site authority must confirm the applicable prerequisites.
The test quotation should include the required measurement records, not merely attendance and a pass certificate. Agree how the load and movement data, setup identification, instrument records and observations will be delivered. Testing that produces no traceable data may leave the designer unable to use the result even when the crew completed its work.
Keep test-foundation identity attached to every result
Assign a unique identifier before each test installation. Record the exact screw type and configuration, its location, installation record and relevant site-zone reference. The test report should identify which physical specimen produced each result, including any extensions, head components or approved installation modifications.
Photographs should show enough context to establish the setup and location. A close-up of a gauge displaying a force is not a complete test record. Ask for the planned load direction and measurement reference arrangement to be documented in the report, together with deviations approved during the work. The engineer, not the purchasing coordinator, determines whether those deviations preserve the test's validity.
Do not merge results from different screws into a single unlabeled curve. If the report summarizes a group, preserve the individual records and explain the grouping. An unusually favorable result should not erase a less favorable result from another required location. The design reviewer needs the actual spread and the reasons for exclusions.
Require a clear disposition for incomplete tests. Equipment limitations, interrupted work, unexpected movement or an unplanned obstruction should remain visible. A retest may be appropriate under the approved plan, but it should reference the original event. Replacing a failed or incomplete record with a new clean page without explanation destroys useful traceability.
Treat installation torque as a controlled parameter
Ask the system owner and designer what installation parameters must be recorded and how they relate to the accepted site evidence. Do not assume that torque has the same meaning across all ground-screw designs, soil conditions and installation processes. A high reading can be a reason for investigation rather than a simple proof of adequate capacity.
KRINNER's environmental product declaration, section 2.8 describes an installation sequence in which torque is established through prior investigations and records are retained. Its discussion of deeper installation using extensions is explicitly associated with the V-series. This product-specific description does not authorize arbitrary extensions, prescribe a universal torque-to-capacity factor or replace the current instructions for the proposed system.
The production record should identify the measurement method and the equipment used, including how its indicated value is interpreted under the approved process. If a hydraulic pressure indication is used as part of the method, ask for the applicable relationship and its verification. A handwritten number labeled torque is incomplete when nobody can establish how it was obtained.
Define the response to readings outside the accepted process before installation begins. The instruction may require a hold and technical review. Purchasing should make approved replacement components available when needed, but it should not advise an operator to keep driving, add an improvised extension or relocate a foundation without the responsible release.
Define the exception route for refusal, alignment and head position
The installation plan should anticipate situations in which the specified foundation cannot be installed as intended. Agree a recording and escalation route for obstruction, unexpected resistance, alignment issues or a head position outside the approved geometry. The immediate requirement is a traceable exception, followed by an authorized disposition.
A useful exception record contains the foundation identifier, intended configuration, observed condition, relevant measurements and photographs. Add the installer, date and equipment reference. Describe what actually happened without rewriting the entry to match the intended outcome. This allows the designer to assess the issue and avoids passing an undocumented problem to the rack crew.
Potential remedies are project decisions. Moving a foundation, changing its configuration or altering the rack connection can affect the accepted design. The change record should identify which drawings, calculations and quantities are affected. A verbal instruction may allow urgent coordination, but the final release needs an identifiable written record before the changed assembly is treated as approved.
Also define how unresolved positions are marked on site and in the order schedule. A foundation awaiting review should not appear as available simply because it is physically present. Distinguish installed, inspected, accepted and released for the next trade. Those states help prevent a rack installation from concealing an unresolved foundation issue.
Compare hypothetical submissions without choosing by torque alone
Consider a fictional project with two ground zones, A and B, and a planned total of 120 foundations. The designer's schedule calls for separate evidence for both zones. Supplier One returns a test report for zone A and proposes the same screw and installation parameter everywhere. Supplier Two returns records for both zones but leaves several zone-B positions on hold pending review. These are invented document examples, not actual test results or recommended project quantities.
The buyer should not prefer Supplier One merely because its return has no outstanding items. Ask whether the responsible designer has accepted extension of the zone-A evidence to zone B. If not, the missing basis remains a hold point. Supplier Two's explicit exceptions may make its submission more transparent, although its unresolved items still need closure before the affected foundations can be released.
Now imagine a supplier presents a tensile test and labels it proof of all foundation loads. The useful follow-up is to compare the result with the accepted test plan and ask which other required directions or combined effects remain unresolved. Do not convert the tensile number into a lateral or compressive value using an undocumented factor.
Finally, suppose the production log contains 120 location rows but only 116 unique identifiers because four were duplicated. The log is not complete merely because its row count equals the order quantity. Reconcile unique locations against the accepted site schedule, identify the missing records and preserve the correction history. This simple document check prevents a clerical total from concealing unverified positions.
Follow one location across the release documents
Use this illustrative return row to test whether a supplier's documents actually join together. The labels are invented identifiers, not product recommendations or tested configurations.
On small screens, swipe or scroll sideways to read every column. Keyboard users can focus the table and use the arrow keys.
| Release field | Hypothetical return | Check before accepting the row |
|---|---|---|
| Location and ground zone | B-042, zone B | Both exist on the accepted site plan |
| Screw and head | Configuration S-B, head H-2 | Both match the released drawing revision |
| Design basis | Foundation schedule R3 | The referenced reaction and interface revisions agree |
| Test basis | Program TP-04, results B-T2 | The designer has accepted applicability to this location or group |
| Installation exception | EX-07, closed by named reviewer | Closure explicitly covers the as-built configuration |
If the shipment supplies head H-3 instead, the row remains unresolved until the appropriate reviewer accepts that exact substitution. An unchanged unit price, the same screw length or a successful test of H-2 does not close the interface change. This check verifies the continuity of an already approved design record; it does not turn the purchasing coordinator into the foundation designer.
Inspect delivered components against the released configuration
Receiving inspection should establish identity before parts are dispersed across the site. Match the supplied product designation, dimensions and head configuration to the released order. Retain lot or delivery references and the required manufacturer documentation. Use the project's inspection plan rather than inventing a universal dimensional tolerance for all ground screws.
Check visible condition under the agreed acceptance criteria. Damage, unidentified components or an unapproved configuration should be segregated for disposition. Do not repair coatings, modify holes or straighten components using an improvised site practice. Request the applicable manufacturer's instruction and the project's acceptance for the proposed remedy.
The steel material-certificate guide can help structure traceability for specified steel components. Material records support identity and specified material properties; they do not establish soil capacity. Similarly, coating documentation answers a different question from the load-test package. Keep the evidence chain connected without treating one certificate as proof of everything.
Where different foundation types arrive together, label packages by the accepted schedule and preserve identity after unpacking. A small difference in a head component may be difficult to recognize after installation. Make the logistics plan support the design distinction so the installer does not have to infer the correct part from memory.
Make the commercial comparison reflect the released scope
Request separate prices for the accepted base configuration, approved alternatives and unresolved options. Include investigation, test installation, reporting, production installation and final inspection where these services are part of the offer. List exclusions clearly so the owner can compare complete scopes rather than component prices that hide different obligations.
Define when quantities become firm. A preliminary array layout may change after site investigation or foundation design. The purchase order should state which release permits manufacturing or delivery and how changes are handled. Avoid presenting an early budget quantity as the final engineered count simply because a supplier needs a number to prepare a quotation.
Ask for written commercial terms for replacement of rejected components, additional work after an approved design change and rescheduling caused by site access or unresolved technical information. These are negotiation items, not standard promises this guide can make on behalf of a supplier. Keep commercial agreement separate from technical approval.
Send the site-zone plan, rack-interface drawing and foundation evidence schedule with your RFQ. Identify confirmed facts, missing decisions and the requested supply scope. This gives a supplier a useful basis for a quotation without asking it to guess soil capacity, a design life, available stock or an installation deadline.
Close the foundation record before handing over to the next trade
The final register should reconcile the designed locations, delivered configurations, installed identifiers and accepted exceptions. Each released location needs the evidence required by the project plan. If a group release is permitted, the record should identify the grouping and the responsible acceptance rather than imply that unrecorded locations were individually tested.
Retain the as-built geometry and approved changes with the rack interface documents. Later maintenance or replacement work may depend on what was actually installed, not only what was originally ordered. Preserve superseded documents in a clearly marked history so a future reviewer can understand why a foundation differs from an early drawing.
Record open restrictions in the handover. If a portion of the site remains on hold, show it in both the digital schedule and the site's coordination process. Do not allow a general completion certificate to erase location-specific exceptions. The accepted handover should state precisely which scope is complete and who owns any remaining work.
Buyer FAQ
Can I select a ground screw only by its length and diameter?
Those dimensions identify part of the product, but they do not establish suitability for a particular foundation. Request the accepted configuration, soil basis, design references and required test evidence. The connection at the top and the installation conditions also need to match the reviewed system. A catalog selection can support early discussion without becoming the final project release.
Does higher installation torque always mean better capacity?
Do not use that rule across unrelated products or site conditions. Ask how the proposed system's installation parameters were established and what readings are acceptable under the project procedure. An unexpected reading should follow the agreed exception route. The buyer should preserve the measurement record and responsible interpretation rather than invent a universal conversion from torque to load capacity.
Is a pull-out test sufficient for every foundation decision?
Only the responsible designer can determine which tests are required for the project's loading and ground conditions. Compare the submitted test direction and configuration with that accepted plan. A tensile result does not automatically establish all other required behavior. If the plan calls for additional evidence, keep the relevant release open until it is accepted or the plan is formally revised.
Can a screw be moved a little when it hits an obstruction?
A moved foundation changes the as-built location and may change the rack interface or load distribution. Follow the approved exception process and obtain the responsible disposition. Record the original location, observed obstruction and accepted change. Do not rely on an informal instruction that the difference is small without identifying who has reviewed its implications for this project.
Does galvanizing guarantee the required service life in any soil?
No universal service-life conclusion follows from that word alone. Ask the designer to identify the durability basis for the actual ground environment and the specified component. Obtain the applicable material and coating documents and the treatment of damage. Do not substitute a generic corrosion statement for the project-specific assessment or claim a warranty that the named supplier has not provided.
What if the test contractor cannot complete the planned test?
Retain the incomplete record and the reason, then ask the responsible reviewer for a disposition. The response may require different equipment, another location or additional investigation under an approved plan. Do not delete the first result or relabel an equipment limit as a passing foundation result. Any revised commercial scope should remain linked to the technical decision that required it.
What information should be sent before requesting a quotation?
Provide the site location and plan, available investigation, rack reactions and interface drawing, required foundation scope and current approval status. Identify preliminary quantities and unresolved design decisions explicitly. Ask the bidder to return its proposed configuration, evidence references, exclusions and commercial terms. This is more useful than requesting a universal load rating for an unspecified screw in unspecified ground.
Buy the evidence chain with the components
A ground-screw order becomes actionable when the site information, foundation design, test basis, delivered identity and installation records describe the same accepted configuration. Preserve the distinction between a useful preliminary quotation and a released foundation package.
Use the solar mounting category to define your component enquiry, then send the project documents and open questions. The procurement goal is a traceable, accepted supply scope supported by the responsible professionals, with no guessed soil capacity or unverified performance promise.