Accept a PV module PAN file for a defined purpose only after identifying its owner and revision, matching its parameters to the offered module and documenting a reproducible software import. A recognizable filename, nominal wattage or attractive energy result does not establish that the file represents the product being purchased. Keep the model-file decision separate from approval of the physical module and the complete project simulation.
A PAN file is a PVsyst module-definition file used to store and exchange a created or modified module representation, as described in the official database documentation. It can travel through several organizations before reaching purchasing: a manufacturer, testing provider, designer, distributor and project analyst may each supply a copy. The practical question is not simply whether a file exists. It is whether the buyer can explain which copy was accepted, which information supports it, which assumptions remain and who can authorize a later change.
This guide addresses that handoff. It does not teach a complete PVsyst simulation, prescribe model coefficients or validate a supplier's power claim. All comparisons below are hypothetical document-review examples. They are not measurements of an offered product, a SINAWATTS modeling service claim or a forecast of site production.
Define the decision before requesting the file
Start with one sentence describing the intended use. A feasibility comparison, tender evaluation, detailed design and contractual performance assessment can require different evidence and approval owners. A file acceptable for an early comparison should not silently acquire a stronger status when copied into a later project folder.
Write the accepted use beside the product identity. Include the manufacturer name, complete model designation, nominal power variant, construction revision when available and current datasheet revision. If the offered product is a family, ask which members the file represents and how that scope was established. Do not infer applicability across every wattage because the model names share a prefix.
Then name the technical reviewer. Purchasing can check completeness, preserve files and obtain responses, but the responsible analyst must judge the modeling assumptions. The manufacturer should answer product identity and supplied-data questions. A laboratory should explain its measurement report. These responsibilities should remain visible instead of collapsing into a generic request for a "certified PAN."
Use three outcomes: accepted for a stated purpose, returned for a specific clarification, or retained as a provisional assumption. A provisional file can still support a bounded planning exercise when the analyst authorizes that use. It should not support an unqualified product-performance premium or final design acceptance.
Understand what a database entry does and does not establish
PVsyst's official module database guidance explains that module data can come from manufacturers and that users can create or modify module definitions. It also explicitly advises checking database parameters against recent datasheets rather than treating library inclusion as an accuracy guarantee. That is a strong reason to review the actual file used in the project, not merely confirm that a similar product appears in a selection list.
Ask whether the submission is an unchanged database definition, a manufacturer-issued file, a laboratory-supported definition or a locally edited derivative. None of those labels alone settles suitability. They tell the reviewer which evidence and change history to request next.
Preserve the original received file. Record the sender, receipt date, accompanying communication and any declared software version. Assign an internal identifier and, where your document system supports it, a checksum. The checksum helps detect whether two copies differ; it does not authenticate the sender, certify the parameters or establish who approved them.
Keep an editable working copy separate from the received copy. If the reviewer changes a field, create a new revision with a reason and author. A filename such as "final-new-corrected" is a weak substitute for a controlled change record, especially when several bidders use similar module names.
Build a parameter provenance register
A provenance register states where a parameter came from and how it entered the file. It need not repeat every internal software variable in the purchase order. Focus first on fields that identify the product, characterize its electrical behavior or support a claimed advantage in the comparison.
Use four origin categories: transcribed manufacturer information, measured information, fitted model values and software defaults or analyst assumptions. A fifth category, unresolved, is useful when the file contains a value but no one can explain its origin. Do not relabel an unresolved value as measured simply because it has many decimal places.
On small screens, swipe or scroll sideways to read every column. Keyboard users can focus the table and use the arrow keys.
| Parameter group | Source to request | Question for the reviewer |
|---|---|---|
| Product and power variant | Current identified datasheet and supplier confirmation | Does the file represent the exact offered variant? |
| Reference electrical values | Datasheet or applicable measurement report with conditions and units | Are the source definitions and reference conditions consistent? |
| Model coefficients | Fitting record, software default identification or analyst rationale | Is each important value measured, derived or assumed? |
| Dimensions and construction fields | Product drawing or manufacturer data | Does the imported representation match the intended physical module? |
| Optional behavior inputs | Relevant report, declared curve or approved assumption | Is the evidence specific enough for the claimed use? |
Add columns for document revision, page or table, imported value, transformation and disposition. The transformation column matters when an original unit or sign convention differs from the displayed software field. It lets a second reviewer reproduce the step instead of trusting an unexplained number.
Keep the register proportionate. If a parameter has no bearing on the defined purchasing decision, mark that limitation rather than inventing a review requirement. Conversely, a parameter supporting a price premium deserves an explicit source and an identified reviewer, even if the rest of the file is routine.
Separate a measured quantity from a model parameter
Two fields can use similar labels while representing different quantities. PVsyst's model-parameter documentation distinguishes the series-resistance parameter used by its one-diode model from apparent series resistance inferred from the slope near open-circuit voltage. They should not be substituted merely because both descriptions contain "series resistance."
The purchasing consequence is a definition check. When a report, datasheet and model file contain apparently inconsistent resistance values, ask the analyst to identify the quantity, units, method and intended field. The correct response may be an explanation rather than a numerical correction. Editing the model until two differently defined numbers match could make the representation less defensible.
Apply the same discipline to percentage versus absolute temperature coefficients, module-level versus cell-level values, and reported versus fitted quantities. Do not assume that a software label has the same denominator as a spreadsheet heading. Request the conversion or mapping used, including its source and responsible reviewer.
A useful discrepancy note says: "Source table names quantity A; destination field represents quantity B; please provide the supported mapping or explain why the field remains at its stated assumption." This invites a precise answer. "The PAN looks wrong" does not.
Check the denominator in a coefficient before comparing values
Consider a hypothetical datasheet that states a relative power-temperature coefficient of minus 0.30 percent per kelvin, referenced to 400 W. A separate review sheet expresses that coefficient in watts per kelvin. For this arithmetic example, minus 0.30 percent means minus 0.003, so multiplying by the stated reference power gives minus 1.20 W/K. The two differently written values can describe the same local coefficient when their definitions and reference basis agree.
The numbers are invented for a unit-mapping example, not a real module specification or a proposed PVsyst setting. The calculation does not establish a constant coefficient over every temperature, validate the model's temperature response, or justify an energy forecast. It also does not authorize entering a power coefficient into a voltage-coefficient field.
The buyer's return question should identify the quantity, sign, unit, denominator and reference value. Ask the analyst to confirm the meaning of the destination field and document the mapping before making an edit. If the datasheet's denominator is not stated or the field represents a fitted model result, retain the discrepancy until that definition is resolved. Copying the visible numeral alone would lose the relationship the source was describing.
Review reference values before more detailed behavior
Check the complete set of supplied reference electrical values together, not only the nominal power printed in the filename. Record the source conditions and units. Ask the technical reviewer to explain any mismatch between the rated power, the stated maximum-power-point values and the imported model representation.
PVsyst's main module interface documentation separates basic reference data, model parameters, additional data, measured data and dimensions or technology information. That organization is useful for a review checklist: matching one category does not establish that the remaining categories are correct.
For a simple hypothetical consistency check, suppose a document lists a maximum-power-point voltage of 40 V and current of 10 A under the same stated conditions. Their product is 400 W. If a copied file is described as a 500 W variant, the reviewer has a specific identity or transcription question to resolve. The calculation does not establish an acceptable tolerance, real module performance or a reason to overwrite a value without authorization.
Investigate first whether the documents concern different variants or revisions. Check conditions and rounding before declaring a contradiction. Preserve both source statements and the supplier's explanation. A corrected datasheet, a revised file and an approved modeling assumption are different resolutions and should be recorded accordingly.
Ask how measured evidence entered the model
A report can accompany a PAN file without having been used to create it. Request the connection: identify the report, the relevant sample or product scope, the usable data, the fitting procedure and the resulting file revision. If the file was produced earlier than the cited measurements, ask whether it was actually revised afterward.
The PVsyst measured-data documentation describes tools that use low-light information and measured current-voltage curves to elaborate the module model. This confirms that measurements and model construction are distinct stages. Merely receiving both documents does not prove a traceable transformation between them.
For a procurement review, ask the analyst to select representative supported conditions and compare the model response with the supplied evidence. Have that reviewer define the comparison method, uncertainty treatment and acceptance basis. Do not invent a universal percentage agreement or require unsupported extrapolation outside the available measurements.
Use the separate low-light evidence guide when the underlying irradiance-temperature data are the problem. Use the incidence-angle modifier guide for optical-curve scope. The present task is to establish which evidence reached which accepted file revision.
Verify the imported definition, not just the attachment
Ask the designated analyst to import the exact submitted copy into the agreed software environment and retain a short acceptance record. Identify the software version, file identifier, import date, operator and any warnings or manual changes. The reviewer should distinguish a successful import from a technically accepted model.
Compare the imported identity and important displayed fields with the provenance register. This can expose an incorrect variant selected from a local database, a stale working copy or a manual edit that did not reach the transmitted file. A screenshot is useful only when its file and software context are clear.
Record whether the file was saved again after import. If the saved file differs, explain whether the software normalized its representation or a person changed a parameter. Preserve the received artifact and the accepted derivative separately. The objective is reproducibility, not a demand that every software version serialize a file in exactly the same way.
Do not ask a supplier to eliminate every warning without understanding it. Have the analyst classify warnings as resolved, accepted with a stated limitation, or blocking for the intended use. A silent screenshot is not evidence that no warnings occurred. Likewise, a warning alone does not prove the physical module is defective.
Freeze the comparison before interpreting an energy difference
A file-review exercise can easily become a claim that one module produces more energy. Keep the analysis controlled. Ask the project analyst to identify what changed between scenarios and which inputs remained fixed. Weather, layout, inverter configuration, losses and other project assumptions belong to a wider model review and can obscure the effect of a module-file revision.
For an initial diagnostic comparison, the analyst may hold the project definition fixed and change only the identified module-file revision, where that comparison is meaningful. Record that purpose. It is not a complete redesign or a contractual performance assessment, particularly if the physical module change would require a different layout or electrical configuration.
If a favorable result depends on an unsupported coefficient, mark the result as conditional and request the missing evidence. Do not silently choose the less favorable coefficient as a substitute for technical review either. The defensible outcome is an approved assumption with a scope and owner, or a corrected evidence package.
When requesting solar accessories alongside a module package, include the module identity and intended project configuration. Send RFQ with the accepted file identifier, relevant datasheet and unresolved parameter questions so the inquiry describes the evidence needed. Product suitability, documentation and commercial terms require confirmation for the actual project.
Compare two hypothetical files without declaring a winner
Assume a buyer receives two files for the same offered module designation. File A is supplied by the manufacturer with a dated datasheet reference. File B arrives from an intermediary and is said to give a better project result. The following comparison is invented solely to demonstrate a document decision; it contains no measured product performance.
On small screens, swipe or scroll sideways to read every column. Keyboard users can focus the table and use the arrow keys.
| Review item | Hypothetical File A | Hypothetical File B | Required action |
|---|---|---|---|
| Product identity | Complete designation and datasheet revision | Same family name, suffix missing | Confirm the represented variant before comparison |
| Parameter changes | Source categories recorded | Selected coefficients changed without a record | Request change reasons and supporting evidence |
| Import check | Identified version and retained review output | Screenshot without file identifier | Reproduce the import using the received copy |
| Intended use | Accepted for a preliminary comparison | Described as approved for all projects | Obtain a bounded approval from the responsible reviewer |
The table does not prove A is accurate or B is inaccurate. It shows that B's stated status exceeds its documented evidence, while A still needs the technical review appropriate to its intended use. The supplier can close B's gaps by providing the missing identity, sources and reproducible record.
Record the outcome in terms of the decision being made: which file may enter the tender comparison, what remains provisional, and which evidence is due before a later milestone. This is more useful than choosing a preferred filename and allowing the unresolved assumptions to disappear from the purchasing record.
Close a file discrepancy with a return record
Consider a hypothetical file whose nominal power and product name match the inquiry, but whose construction suffix is absent. The supplier responds that the missing suffix is only a naming convention. That statement is useful, yet the buyer still needs a link to the offered construction and the exact file being approved. Record the supplier response with the model identifier, datasheet revision and file checksum or controlled reference; ask the technical owner to accept or reject the stated equivalence.
If the supplier instead issues a new file, retain the original and request a field-level change list. The analyst can then determine whether the correction changes only identification or also affects the model response. A new filename is not itself a change explanation. A report regenerated from an unrelated local copy is also not evidence that the transmitted correction was reviewed.
The return record should contain the original question, supplier response, revised artifacts, reviewer disposition and authorized use. Give unresolved items their own owners and milestones. For example, identity may be closed while the low-light assumption remains provisional for tender comparison. Keeping those decisions separate prevents one completed action from being interpreted as approval of every performance input.
When the discrepancy is closed, send the accepted file identifier back to the supplier and project analyst through the agreed project process. Ask them to use that identifier in subsequent deliverables. This is a document-control recommendation, not a claim that every organization must adopt a particular software tool or file format.
Control changes after the file is accepted
A revised file should arrive with a change list, not just a newer date. Ask what changed, why it changed, which source supports it and which earlier analyses may be affected. Distinguish a correction to an existing representation from a new physical module construction or power variant.
Use the same approach when only the product changes. If a module construction revision appears while the PAN filename remains unchanged, ask the manufacturer and analyst whether the previous evidence still applies. Do not prescribe a universal retest list; require the responsible technical owner to document the applicability decision.
Keep a register of the projects or tender comparisons that used each accepted revision. When a significant correction is approved, that register helps identify which results need review. Do not overwrite earlier analysis records. They should continue to show what was known and authorized at the time.
Agree who can distribute the accepted file externally. Commercial confidentiality or licensing restrictions may affect the supporting report or model deliverable. If full raw data cannot be shared, request an agreed review arrangement or a sufficient documented explanation; do not invent access rights or treat confidentiality as automatic proof that the claim is valid.
Make the RFQ deliverables reviewable
A concise RFQ can ask for the exact product designation, current datasheet, original PAN file, source declaration, parameter-change record and software context. Add the intended use, the reviewer and the conditions that must be resolved before award. Request supplier confirmation of the deliverable scope rather than assuming a file is included in every module quotation.
Separate the commercial schedule from technical approval. Ask the supplier to identify whether evidence is already available, needs clarification or requires additional agreed work. Do not publish a standard turnaround time, testing charge or minimum order quantity without a project-specific quotation.
Define the response format for open questions. A useful answer identifies the disputed field, quotes or points to its source, explains the mapping and names the revised file if one is issued. A broad declaration that the product "meets requirements" is insufficient when the unresolved question concerns a specific coefficient or revision.
For the release record, retain the received file, accepted file, source register, import review, unresolved limitations and approval. If acceptance is conditional, name the condition and expiry or milestone for resolution. This makes it possible to close the purchase action without confusing a provisional model with a fully supported performance commitment.
Buyer FAQ
Does a PAN file certify the module or guarantee project output?
No. It is a model-data artifact, and its acceptance has to state the intended use and supporting evidence. Physical product qualification, contractual guarantees and site-energy assessment are separate decisions. Ask the relevant technical and commercial owners to identify what each document actually supports.
Is a manufacturer-issued file automatically preferable to an edited file?
Its origin is valuable, but origin alone does not establish that it matches the offered revision or contains no transcription issue. An edited file can be useful when its changes are supported and approved. Compare identity, sources, change history and reproducibility before deciding which copy is appropriate.
What should happen when the datasheet and imported values differ?
Preserve both records and identify the exact field, unit, reference condition and revision. Ask the manufacturer and analyst whether the difference reflects rounding, a variant mismatch, a definition difference or a correction. Do not overwrite either document simply to make the numbers agree.
Can missing model coefficients be filled with software defaults?
The analyst may use defaults or other assumptions when appropriate for the declared purpose, but they should remain identified as assumptions. Their presence is not evidence of a measured product advantage. Ask which conclusions depend on them and whether additional evidence is needed before a later purchasing milestone.
Must buyers obtain every raw test point before shortlisting a module?
Not necessarily. Agree the evidence depth with the technical reviewer and the decision being supported. A preliminary comparison can have a different scope from a final performance assessment. Any restricted access, omitted evidence and unresolved assumptions should be visible rather than silently treated as complete.
Why keep the software version and an import record?
They help another reviewer reproduce the accepted representation and distinguish the transmitted file from a local or modified copy. Successful import is only a completeness check; the technical reviewer must still assess parameter meaning and suitability. Record warnings and manual changes together with their disposition.
What information should accompany a PAN-file-related inquiry?
Provide the offered module designation, datasheet revision, exact received file, intended use, software context and a concise list of disputed fields. Include the supporting reports you are authorized to share. Send RFQ with these references so the discussion can address a defined evidence gap rather than an unspecified promise of higher yield.
Release a file with a bounded decision
The final record should answer five questions: which product, which file, which sources, which software representation and which approved use. If any answer is missing, keep that limitation attached to the purchasing decision. An organized evidence chain allows later corrections to be reviewed without pretending that a filename or library listing proves performance.